Bungalow to two semi-detached houses
During the construction of one of our Bushey sites we were approached by one of the local residents to say that he had a site with planning permission to construct a pair of semi-detached houses almost identical to the ones we were currently building. After some negotiation we agreed a price and work started a few months later. We altered some of the internal design and the build to complete the project in 52 weeks.
SOME OF THE TASKS THAT WE SUCCESSFULLY COMPLETED DURING THE CONSTRUCTION:
- Complete demolition and removal of the existing bungalow
- Installation of block and beam floor
- Installation of attic truss roof with large crown roof
- Underfloor heating to the ground floor
- Level threshold joining the kitchen / diner through Bi-fold doors and onto the external patio and garden
- Having a building that blends into the street scene as if it was always there